Resurfacing of I-75 Business Loop

by Chelsea Goodwin
Thursday, September 3, 2020

On Tuesday, September 1, 2020, MDOT released this update regarding the resurfacing of I-75 Business Loop in downtown Grayling.  Please allow additional time for safe travels.  We apologize for any inconvenience this may cause.

 

  HIGHWAY:  Grayling I-75 Business Loop (BL) 

  START DATE:  Tuesday, Sept. 8, 2020

  ESTIMATED END DATE:  Friday, Oct. 30, 2020

  PROJECT:

 The Michigan Department of Transportation (MDOT) will invest $953,000 to resurface 0.9 miles of I-75 BL in Grayling from the northbound and southbound I-75 ramps to north of the Lake State Railroad.

 The work will require a 72-hour closure of the northbound off ramp; the schedule of that closure will be announced at a later date.

 For project details and a map, visit Mi Drive.

 

TRAFFIC RESTRICTIONS:

This work will require single-lane closures and traffic shifts. All paving will be done at night.

 SAFETY BENEFITS:

This work includes new sidewalk ramps meeting Americans with Disabilities Act (ADA) standards and new pavement markings.